A team's average completed work is 20 points per Sprint. Its next Sprint includes a major holiday. How should the team use the historical figure?

Published
  1. Commit to at least 20 points because velocity is a quota
  2. Double all estimates so the same amount of work appears larger
  3. Treat it as planning evidence and account for the reduced capacity
  4. Use 20 points as a promise for every team in the organization