A team's average completed work is 20 points per Sprint. Its next Sprint includes a major holiday. How should the team use the historical figure?
Published
- Commit to at least 20 points because velocity is a quota
- Double all estimates so the same amount of work appears larger
- Treat it as planning evidence and account for the reduced capacity
- Use 20 points as a promise for every team in the organization