A work package's scope is understood, but its output is missing from the WBS. What should the team do?
Published
- Add the output only to an individual's private notes
- Treat the WBS as a list of staff names
- Remove its acceptance criteria
- Include the required scope in the controlled WBS through the appropriate planning process