An accepted risk response says to switch suppliers when a delivery forecast exceeds ten days late. The trigger occurs. What should the manager do?
Published
- Execute the planned response within the agreed authority
- Pretend the trigger did not occur
- Create an unrelated stakeholder survey instead
- Wait until final project closure to reassess