An accepted risk response says to switch suppliers when a delivery forecast exceeds ten days late. The trigger occurs. What should the manager do?

Published
  1. Execute the planned response within the agreed authority
  2. Pretend the trigger did not occur
  3. Create an unrelated stakeholder survey instead
  4. Wait until final project closure to reassess