An estimate depends on an external expert being available in June. What should the team do with that dependency?
Published
- Remove the expert's work from the plan
- Validate availability and track the assumption or constraint explicitly
- Assume a calendar invitation guarantees attendance
- Wait until the work is overdue to contact the expert