An estimate depends on an external expert being available in June. What should the team do with that dependency?

Published
  1. Remove the expert's work from the plan
  2. Validate availability and track the assumption or constraint explicitly
  3. Assume a calendar invitation guarantees attendance
  4. Wait until the work is overdue to contact the expert