At a status date, earned value is $60,000 and actual cost is $75,000. What is the cost performance index?

Published
  1. 0.80, indicating the project is necessarily late
  2. $15,000, indicating favorable cost variance
  3. 0.80, indicating less value earned per dollar spent than planned
  4. 1.25, indicating favorable cost efficiency