During a Sprint, a stakeholder directly asks a Developer to substitute unrelated work that would endanger the Sprint Goal. What is the best response?

Published
  1. Keep the request secret until the Sprint Review
  2. Have the Scrum Master add it unilaterally
  3. Discuss the request with the Product Owner and preserve the Sprint Goal
  4. Accept immediately because the stakeholder is a customer