During a Sprint, Developers learn that the original plan needs adjustment to achieve the Sprint Goal. What should they do?
Published
- Adapt the Sprint Backlog while collaborating as needed with the Product Owner
- Wait until the project ends before changing any task
- Ask the sponsor to assign every task personally
- Change the Sprint Goal privately without consultation