During a Sprint, Developers learn that the original plan needs adjustment to achieve the Sprint Goal. What should they do?

Published
  1. Adapt the Sprint Backlog while collaborating as needed with the Product Owner
  2. Wait until the project ends before changing any task
  3. Ask the sponsor to assign every task personally
  4. Change the Sprint Goal privately without consultation