Earned value is $72,000 and planned value is $60,000. What does SPI = 1.20 indicate?

Published
  1. More work has been earned than planned at this point
  2. The project is guaranteed to finish 20% early
  3. Every deliverable has been accepted
  4. Costs are exactly 20% below budget