Two parallel paths take 12 and 9 days. An activity only on the 9-day path slips by 2 days, with no other constraints. What happens to the completion date?

Published
  1. It remains unchanged
  2. It advances by 2 days
  3. Both paths become critical
  4. It slips by 2 days