Two projects require the same specialist during the same week. What should their managers do first?

Published
  1. Delete the specialist's activities from both schedules
  2. Resolve it solely by changing task names
  3. Coordinate priorities and feasible allocations with the resource owner
  4. Both assume full-time availability