Two team members disagree about a technical approach. Both have useful evidence and there is time to discuss it. Which response best supports a durable resolution?
Published
- Split implementation equally even if the approaches are incompatible
- Ask the members to avoid discussing the disagreement
- Facilitate a collaborative discussion of needs, evidence, and options
- Choose the approach of the more senior employee without discussion