A budget includes a reserve for an identified supplier-delay risk and a separate reserve for unforeseen in-scope work. Which distinction is correct?

Published
  1. Both reserves are earned value already achieved
  2. The identified-risk reserve is contingency; the unforeseen-work reserve is management reserve
  3. Management reserve is always available to any team member without approval
  4. Contingency is reserved only for work deliberately excluded from scope