A change-control board rejects a request after impact analysis. The requester continues telling the team it is approved. What should the manager do?

Published
  1. Delete the rejection record
  2. Let each team choose which message to follow
  3. Implement the request secretly to avoid disagreement
  4. Communicate the recorded decision and clarify the authorized work with the affected parties