A change-control board rejects a request after impact analysis. The requester continues telling the team it is approved. What should the manager do?
Published
- Delete the rejection record
- Let each team choose which message to follow
- Implement the request secretly to avoid disagreement
- Communicate the recorded decision and clarify the authorized work with the affected parties