A community group raises a credible concern that a construction project's delivery approach will obstruct access to essential services. What should the manager do?
Published
- Engage affected stakeholders, assess impacts, and evaluate mitigations through the project process
- Wait until construction ends to assess the concern
- Ignore the concern because the group is not funding the project
- Promise every requested change before impact assessment