A contractor is leaving, and key design decisions exist only in chat messages. What should be prioritized?

Published
  1. Archive the chat without checking access or comprehension
  2. Assign ownership to someone without a handover
  3. Capture rationale and validate the receiving team's understanding before departure
  4. Wait for a future defect to identify what was lost