A contractor is leaving, and key design decisions exist only in chat messages. What should be prioritized?
Published
- Archive the chat without checking access or comprehension
- Assign ownership to someone without a handover
- Capture rationale and validate the receiving team's understanding before departure
- Wait for a future defect to identify what was lost