A critical supplier is on schedule but has not produced required quality evidence. What should the manager do?

Published
  1. Evaluate compliance with the contract's deliverable and verification requirements
  2. Accept the work based only on its delivery date
  3. Remove the evidence requirement privately
  4. Cancel the entire project before reviewing the agreement