A customer accepts the main product, but an agreed data export for operations is unfinished. What should the manager do before closure?
Published
- Assume operations will create it without agreement
- Resolve the remaining obligation or obtain an authorized documented transition arrangement
- Mark the export complete because the main product was accepted
- Close the project and omit the export