A customer accepts the main product, but an agreed data export for operations is unfinished. What should the manager do before closure?

Published
  1. Assume operations will create it without agreement
  2. Resolve the remaining obligation or obtain an authorized documented transition arrangement
  3. Mark the export complete because the main product was accepted
  4. Close the project and omit the export