A customer asks for a capability not represented in the approved scope. What should the manager establish before planning implementation?

Published
  1. An immediate rejection based only on the request's timing
  2. A promise that it has no cost or schedule effect
  3. The actual requirement and its relationship to authorized scope and value
  4. A task assignment before understanding the need