A customer requests a significant feature directly from Developers during a Sprint. The team has an agreed Sprint Goal. What is the best response?

Published
  1. Refuse to discuss any new need until final project closure
  2. Change the Sprint Goal privately to fit the request
  3. Discuss the need with the Product Owner and assess options without undermining the Sprint Goal
  4. Implement it immediately because the customer asked