A customer requests a significant feature directly from Developers during a Sprint. The team has an agreed Sprint Goal. What is the best response?
Published
- Refuse to discuss any new need until final project closure
- Change the Sprint Goal privately to fit the request
- Discuss the need with the Product Owner and assess options without undermining the Sprint Goal
- Implement it immediately because the customer asked