A customer says the release is late, but the project team believes the agreed date refers to pilot availability. What should happen first?

Published
  1. Apply penalties to the team immediately
  2. Reconcile the milestone meaning and acceptance expectations with the customer
  3. Change the date privately in the schedule
  4. Assume the customer's interpretation is irrelevant