A customer says the release is late, but the project team believes the agreed date refers to pilot availability. What should happen first?
Published
- Apply penalties to the team immediately
- Reconcile the milestone meaning and acceptance expectations with the customer
- Change the date privately in the schedule
- Assume the customer's interpretation is irrelevant