A delayed external approval is now blocking the team's critical work. The risk had been recorded earlier. What should the manager do?
Published
- Keep it only as a future risk with no issue response
- Manage the realized issue, escalate appropriately, and evaluate feasible workarounds
- Remove the approval requirement without authority
- Start more dependent work that cannot proceed