A fixed-price supplier requests payment for work outside the agreed scope. What should the manager do first?

Published
  1. Reject the request solely because the contract is fixed price
  2. Review the agreement and the change history with the relevant procurement parties
  3. Pay immediately because the supplier performed the work
  4. Ask Developers to negotiate privately without procurement context

Comments — 0