A fixed-price supplier requests payment for work outside the agreed scope. What should the manager do first?
Published
- Reject the request solely because the contract is fixed price
- Review the agreement and the change history with the relevant procurement parties
- Pay immediately because the supplier performed the work
- Ask Developers to negotiate privately without procurement context