A functional manager and product owner disagree about a specialist's allocation. The project manager does not control the specialist. What is the best response?

Published
  1. Promise both parties full capacity
  2. Assign the specialist full-time unilaterally
  3. Remove the specialist's work from the forecast
  4. Negotiate with the accountable resource owners using priorities and capacity evidence