A functional manager and product owner disagree about a specialist's allocation. The project manager does not control the specialist. What is the best response?
Published
- Promise both parties full capacity
- Assign the specialist full-time unilaterally
- Remove the specialist's work from the forecast
- Negotiate with the accountable resource owners using priorities and capacity evidence