A geopolitical event threatens an imported component that is not yet delayed. What should the manager do?

Published
  1. Remove the import from the schedule without a replacement plan
  2. Treat the event as proof of a certain delivery failure
  3. Wait until the component fails to arrive before recording anything
  4. Assess the scenario, monitor relevant triggers, and evaluate authorized alternatives