A high-performing team is exhausted after repeated emergency releases. A sponsor requests another acceleration. What should the manager do?
Published
- Remove all testing to maintain the date
- Commit first and discuss capacity after the deadline
- Refuse every future change regardless of value
- Present feasible scope and capacity tradeoffs using the team's evidence