A hybrid project has separate infrastructure and software plans that use inconsistent release assumptions. What should the manager do first?

Published
  1. Integrate dependencies, milestones, and planning assumptions with the responsible teams
  2. Approve both plans independently and address conflicts at launch
  3. Require identical delivery methods for all work
  4. Choose the plan with the earlier date without analysis