A late project has completed all its work, so EV equals PV at BAC. What limitation should the manager recognize when interpreting final SPI = 1?

Published
  1. No schedule evidence may be reported after completion
  2. The project must have finished on time
  3. Traditional SPI can return to one at completion despite a late calendar finish
  4. All cost variances must also be zero