A late project has completed all its work, so EV equals PV at BAC. What limitation should the manager recognize when interpreting final SPI = 1?
Published
- No schedule evidence may be reported after completion
- The project must have finished on time
- Traditional SPI can return to one at completion despite a late calendar finish
- All cost variances must also be zero