A new safety requirement takes effect before the planned launch. What should the manager do first?

Published
  1. Confirm applicability with qualified stakeholders and assess the delivery impact
  2. Copy another project's exemption without review
  3. Assume the project is exempt because it began earlier
  4. Wait for a failed inspection