A new stakeholder joins midway and challenges the project's purpose. The team regards the purpose as settled. What should the manager do?

Published
  1. Understand the concern and revisit the shared vision with the appropriate stakeholders
  2. Reject discussion because the charter is signed
  3. Automatically restart the entire project
  4. Let the new stakeholder privately replace the objectives

Comments — 0