A newly assembled team has unclear decision rights and repeatedly waits for the project manager to approve routine actions. What is the best response?
Published
- Clarify delegated authority and team working agreements within organizational boundaries
- Judge the team as unmotivated without discussing responsibilities
- Require written manager approval for every action
- Tell members to ignore all governance until they feel autonomous