A newly assembled team has unclear decision rights and repeatedly waits for the project manager to approve routine actions. What is the best response?

Published
  1. Clarify delegated authority and team working agreements within organizational boundaries
  2. Judge the team as unmotivated without discussing responsibilities
  3. Require written manager approval for every action
  4. Tell members to ignore all governance until they feel autonomous