A predictive project has a schedule baseline. A customer requests a new interface that would add three weeks and increase costs. What should the manager do next?

Published
  1. Update only the scope statement and ignore schedule and cost
  2. Tell Developers to start immediately and request approval later
  3. Submit the documented request with integrated impacts to the authorized change process
  4. Reject the request solely because the baseline exists