A predictive project receives an approved change that affects scope, schedule, and procurement. What should the manager do next?
Published
- Integrate the approved change into the affected plans and communicate the authorized state
- Treat approval as proof that no risk remains
- Update only the task title
- Ask the team to continue using the superseded baseline