A predictive project receives an approved change that affects scope, schedule, and procurement. What should the manager do next?

Published
  1. Integrate the approved change into the affected plans and communicate the authorized state
  2. Treat approval as proof that no risk remains
  3. Update only the task title
  4. Ask the team to continue using the superseded baseline