A product backlog is large, and several items are too vague for near-term delivery. What should the manager support?

Published
  1. Estimate every vague item to the nearest hour
  2. Remove all stakeholder participation from refinement
  3. Collaborative refinement into understandable, valuable items with suitable acceptance criteria
  4. Start all items to learn faster