A project affects community access to a public facility. Community representatives were omitted from the stakeholder register. What should the manager do?

Published
  1. Ignore them because they are not contract signatories
  2. Promise every requested change before analysis
  3. Update stakeholder analysis and engage representatives on the actual impact
  4. Wait for formal litigation before communication