A project affects community access to a public facility. Community representatives were omitted from the stakeholder register. What should the manager do?
Published
- Ignore them because they are not contract signatories
- Promise every requested change before analysis
- Update stakeholder analysis and engage representatives on the actual impact
- Wait for formal litigation before communication