A project can exploit a favorable supplier discount only if procurement acts before a stated deadline. What response is most appropriate?

Published
  1. Treat the discount as a guaranteed saving before approval
  2. Purchase unrelated items to use the discount
  3. Assign an owner and plan the authorized action needed to realize the opportunity
  4. Ignore it because risk management concerns only threats