A project charter emphasizes faster onboarding, but the operations team measures success as fewer support calls. The teams are making conflicting design choices. What should the manager do first?

Published
  1. Choose the metric favored by the largest team
  2. Facilitate agreement on a shared outcome and measurable success criteria
  3. Escalate a request to replace the operations lead
  4. Require both teams to finish their separate designs before discussion