A project charter emphasizes faster onboarding, but the operations team measures success as fewer support calls. The teams are making conflicting design choices. What should the manager do first?
Published
- Choose the metric favored by the largest team
- Facilitate agreement on a shared outcome and measurable success criteria
- Escalate a request to replace the operations lead
- Require both teams to finish their separate designs before discussion