A project creates value for one division but shifts substantial operating costs onto another. What should the manager bring to governance?
Published
- Only the sponsoring division's reported savings
- An enterprise-level view of benefits, costs, and affected stakeholders
- A rule that costs after handover never matter to the project business case
- A recommendation to hide the transferred costs in operations