A project creates value for one division but shifts substantial operating costs onto another. What should the manager bring to governance?

Published
  1. Only the sponsoring division's reported savings
  2. An enterprise-level view of benefits, costs, and affected stakeholders
  3. A rule that costs after handover never matter to the project business case
  4. A recommendation to hide the transferred costs in operations