A project dashboard shows all tasks green, yet the end-to-end service fails during integration. What is the best improvement?

Published
  1. Change every task status to red permanently
  2. Measure only the number of completed tasks more frequently
  3. Stop integration tests because they conflict with status reporting
  4. Include integrated outcome and acceptance evidence alongside task status