A project forecast uses last quarter's throughput, but half the team has changed and the next work is unfamiliar. What should the manager communicate?

Published
  1. No forecast under any circumstances
  2. The old forecast as an exact guarantee
  3. A revised forecast with explicit assumptions and uncertainty
  4. A hidden fixed delay added without explanation