A project forecast uses last quarter's throughput, but half the team has changed and the next work is unfamiliar. What should the manager communicate?
Published
- No forecast under any circumstances
- The old forecast as an exact guarantee
- A revised forecast with explicit assumptions and uncertainty
- A hidden fixed delay added without explanation