A project has a high-impact dependency on an external team's release. What should the manager establish?
Published
- A local schedule with no reference to the external release
- A statement that external work is outside project risk management
- An assumption that the dependency is complete until told otherwise
- A named dependency owner, agreed milestones, monitoring, and contingency options