A project has a high-impact dependency on an external team's release. What should the manager establish?

Published
  1. A local schedule with no reference to the external release
  2. A statement that external work is outside project risk management
  3. An assumption that the dependency is complete until told otherwise
  4. A named dependency owner, agreed milestones, monitoring, and contingency options