A project has EV of $180,000, AC of $200,000, and PV of $190,000. What are its cost and schedule variances?
Published
- CV = -$10,000; SV = -$20,000
- CV = $20,000; SV = $10,000
- CV = $10,000; SV = -$20,000
- CV = -$20,000; SV = -$10,000