A project has PV of $90,000, EV of $81,000, and AC of $75,000. Which statement correctly describes its performance?

Published
  1. It has earned less value than planned but is cost efficient for completed work
  2. It must finish exactly nine days late
  3. It is ahead of plan and over budget for completed work
  4. Its favorable CPI guarantees an on-time finish