A project has PV of $90,000, EV of $81,000, and AC of $75,000. Which statement correctly describes its performance?
Published
- It has earned less value than planned but is cost efficient for completed work
- It must finish exactly nine days late
- It is ahead of plan and over budget for completed work
- Its favorable CPI guarantees an on-time finish