A project has SPI = 1.10 and CPI = 0.85. Which two interpretations are supported? Select 2 answers.
Published
- The project is guaranteed to finish 10% earlier
- More work has been earned than planned at this measurement point
- The total final cost is exactly 15% above BAC in every forecast
- The project is earning less value per cost unit than planned
- Every deliverable has been formally accepted