A project has SPI = 1.10 and CPI = 0.85. Which two interpretations are supported? Select 2 answers.

Published
  1. The project is guaranteed to finish 10% earlier
  2. More work has been earned than planned at this measurement point
  3. The total final cost is exactly 15% above BAC in every forecast
  4. The project is earning less value per cost unit than planned
  5. Every deliverable has been formally accepted