A project is on time and within budget, but the market need it served has substantially declined. What should the manager do?

Published
  1. Continue unchanged because baseline performance defines all success
  2. Spend the remaining budget before reporting the market change
  3. Cancel the project unilaterally without assessing obligations
  4. Reassess the business case and recommend options through governance

Comments — 0