A project meets its technical acceptance criteria, but the sponsor expected a measurable reduction in processing time. What should the manager address?
Published
- Change the historical baseline without explanation
- Declare that technical completion makes all benefit concerns irrelevant
- The relationship between delivered capability, agreed benefits, and the sponsor's expectation
- Promise the benefit without checking adoption and process changes