A project meets its technical acceptance criteria, but the sponsor expected a measurable reduction in processing time. What should the manager address?

Published
  1. Change the historical baseline without explanation
  2. Declare that technical completion makes all benefit concerns irrelevant
  3. The relationship between delivered capability, agreed benefits, and the sponsor's expectation
  4. Promise the benefit without checking adoption and process changes