A project plan includes a regulatory milestone and iterative feature releases. Which two practices best support integrated delivery? Select 2 answers.
Published
- Keep milestone requirements hidden from the delivery team
- Update forecasts using actual progress and unresolved assumptions
- Treat iteration completion as automatic regulatory approval
- Map dependencies and required evidence between the iterative work and the milestone
- Require all future features to be fully specified before any iteration