A project receives several conflicting requirement changes from different business units. What should guide their evaluation?

Published
  1. The order in which the manager opened the emails
  2. Agreed value criteria, dependencies, constraints, and the defined decision authority
  3. Automatic inclusion of every request in the current release
  4. Whichever requester has the largest team