A project receives several conflicting requirement changes from different business units. What should guide their evaluation?
Published
- The order in which the manager opened the emails
- Agreed value criteria, dependencies, constraints, and the defined decision authority
- Automatic inclusion of every request in the current release
- Whichever requester has the largest team