A project requires a decision beyond the manager's delegated budget limit. The sponsor is unavailable, but the governance plan names an alternate authority. What should the manager do?

Published
  1. Wait indefinitely despite the documented alternate
  2. Approve it personally because the decision is urgent
  3. Divide the expense into smaller entries to avoid the limit
  4. Use the defined alternate escalation path with the decision evidence