A project requires a decision beyond the manager's delegated budget limit. The sponsor is unavailable, but the governance plan names an alternate authority. What should the manager do?
Published
- Wait indefinitely despite the documented alternate
- Approve it personally because the decision is urgent
- Divide the expense into smaller entries to avoid the limit
- Use the defined alternate escalation path with the decision evidence