A project team includes contractors and employees whose responsibilities overlap. Decisions are repeatedly reversed because each group assumes the other owns approval. What should be clarified?
Published
- Only each person's preferred communication channel
- Only the reporting frequency
- Only the order of names on the organization chart
- Role responsibilities and accountable decision authority