A project team includes contractors and employees whose responsibilities overlap. Decisions are repeatedly reversed because each group assumes the other owns approval. What should be clarified?

Published
  1. Only each person's preferred communication channel
  2. Only the reporting frequency
  3. Only the order of names on the organization chart
  4. Role responsibilities and accountable decision authority