A project transfers a system to operations. Which two activities best demonstrate meaningful knowledge transfer? Select 2 answers.
Published
- Close the handover after sending an unread email
- Ask the project team to retain every operational task indefinitely
- Operations performs representative tasks using the handed-over material
- The teams resolve observed gaps and confirm ownership of ongoing procedures
- Count slide pages as the sole completion measure